Race Court Full Closure | Monday, August 9 – Friday, September 2 (26 days)
Race Court will temporarily close on Aug. 9 and tentatively reopen on Sept. 2. Crews will be addressing some unforeseen utilities underground as well as completing new utility work during this time. The duration of this closure is anticipated to be 26 calendar days, beginning at 5 a.m. on Monday, Aug. 9. Local and business access will remain open at all times during the closure using the marked detours.
Activities are weather-dependent. Please see map for route and detour information. Trucks must use posted detours due to low bridge north of Franklin at Brighton Boulevard and York Street. Slow speeds advised. Please obey signage and flaggers.